Dortech were contracted by Main Contractors, Willmott Dixon to design, manufacture and install over 500m2 of curtain wall, windows and entrance doors at Building C in Oldham.

This was part of the first phase of Oldham College’s capital development programme, designed by Aedas, that will see its Rochdale Road campus transformed into a 21st century learning hub.

The Construction works completed well ahead of schedule, to an exceptionally high standard. One air test was carried out with no arrising enhancement works required to the buildings facade.

Peter Mason, Operations Manager from Willmott Dixon was delighted with the outcome and stated: “Thank you for your support on Building C in Oldham. We obtained an air leakage of less than 5 and  practical completion dated  1st April 2015 – exactly 52 weeks from signing the contract. Looks great! Please pass our thanks on to your site engineers and your wider design and procurement team”